The Dublin Port Tunnel may close from time to time. Here are details of planned closures

 

North Bound (Port to Airport):

Start Date
Start Time
End Date
End Time
Lanes
Comments
3rd February 2012
23:00
4th February 2012
05:30
1 & 2
Scheduled Maintenance
6th February 2012
23:00
7th February 2012
05:30
1 & 2
Scheduled Maintenance
7th February 2012
23:00
8th February 2012
05:30
1 & 2
Scheduled Maintenance
8th February 2012
23:00
9th February 2012
05:30
1 & 2
Scheduled Maintenance
9th February 2012
23:00
10th February 2012
05:30
1 & 2
Scheduled Maintenance
10th February 2012
23:00
11th February 2012
05:30
1 & 2
Scheduled Maintenance
14th February 2012
23:00
15th February 2012
05:30
1 & 2
Maintenance Closure
24th May 2012
23:00
25th May 2012
05:30
1 & 2
Scheduled Maintenance
30th August 2012
23:00
31st August 2012
01:00
1 & 2
Scheduled Maintenance
4th October 2012
23:00
5th October 2012
01:00
1 & 2
Scheduled Maintenance

 

South Bound (Airport to Port):

Start Date
Start Time
End Date
End Time
Lanes
Comments
3rd February 2012
23:00
4th February 2012
05:30
1 & 2
Scheduled Maintenance
6th February 2012
23:00
7th February 2012
05:30
1 & 2
Scheduled Maintenance
7th February 2012
23:00
8th February 2012
05:30
1 & 2
Scheduled Maintenance
8th February 2012
23:00
9th February 2012
05:30
1 & 2
Scheduled Maintenance
9th February 2012
23:00
10th February 2012
05:30
1 & 2
Scheduled Maintenance
10th February 2012
23:00
11th February 2012
05:30
1 & 2
Scheduled Maintenance
14th February 2012
23:00
15th February 2012
05:30
1 & 2
Maintenance Closure
24th May 2012
23:00
25th May 2012
05:30
1 & 2
Scheduled Maintenance
30th August 2012
23:00
31st August 2012
01:00
1 & 2
Scheduled Maintenance
4th October 2012
23:00
5th October 2012
01:00
1 & 2
Scheduled Maintenance

 

 

NOTE: This forecast is given for INFORMATION only and might change for operational reasons